Things are looking GREEN! The DensGlass, which comes in green sheets is currently being installed on top of the metal sheeting and will be completed this week. Next, an air and vapor barrier will be sprayed on which will result in a change in color of the building to shite/gray. In addition, the roofing is complete for this stage.
Inside the building, the internal wall framing is expected to be complete this week. MEPs (Mechanical, Electrical, Plumbing, Fire Protection) started this week and will be active for a number of weeks.
Elsewhere on campus....The Chapel and Business Office renovation has been completed. Business and Advancement teams will make the move on Aug. 4th and 5th. Asphalt repair on the back parking lot will take place this week.
Coming up....Masonry on the outside of the building will start next week and take about 3 weeks to complete.
Masonry on the outside of the building to start 8/11: 2.5 – 3 weeks to complete.
Keep checking back weekly for more construction updates!